Construction management of EHV & UHV transmission lines-a practical guide

Sahu Biswanath

B. Sc. Engg. Pgdm (HRm), PGDm (E&E), GmPE (IIm-I), India

Online published on 30 May, 2021.

Abstract

Generation projects are generally located in areas nearer to availability of inputs required for power generation such as water, coal, approach roads and having rail transport facilities. The load centers are at different locations depending on its own convenience& load requirements. Hence there is necessity of transmission of bulk power from generation sites to load or consumer points.

Hence the utility of power transmission through EHV/UHV transmission lines. Further for transmission of bulk power from one region of the country to another region also warrants establishment of Transmission lines. The technical as well as social and commercial criteria are very important while construction and erection of EHV and UHV transmission lines. These issues are of public as well as organization importance and hence efforts have been made in this presentation to elaborate in detail.

Top

Keywords

The key words in this paper are Right of Way (ROW), Crop, Tree and land compensation, Clearances, Government stipulations, Commercial issues, Farmer issues, Soil conditions, Forest, Highways, Rly ways approvals etc..

Top

  
║ Site map ║ Privacy Policy ║ Copyright ║ Terms & Conditions ║ Page Rank Tool
749,396,955 visitor(s) since 30th May, 2005.
All rights reserved. Site designed and maintained by DIVA ENTERPRISES PVT. LTD..
Note: Please use Internet Explorer (6.0 or above). Some functionalities may not work in other browsers.